Update on the progress of our new building

Roxell
2 April 2019

The winter break is over and spring is knocking at the door. Just like the weather, our construction project is moving forward into a new phase. We're still nicely on schedule.

update-progress-new-building-roxell-maldegem
update-progress-new-building-roxell-maldegem

The carpentry in the offices has been completed and, in February, we fitted the windows in the lobby area. The brickwork is also finished.

At the end of February, we installed heating in the lobby. The pipes are all laid and the walls have been plastered.

Outside, the scaffolding is gone, so we can finish the sewers and the landscaping. We also started the final work on the roof, after which, the heat pumps will be installed on the roof and the tower crane will be removed from the site.

As you can see, we've made a lot of progress! We're already looking forward to the moment when our employees can move into our new building!